1. CATEGORY
1.0 – River Training (longitudinal structure)
2. DESIGN STATUS
Level II
3. ALSO KNOWN AS
Log or timber cribwall. Note: vegetation, primarily transplants and rooted
plants, can also be inserted into the frontal openings of several proprietary
concrete cribwall systems, e.g., Criblock and Evergreen Walls (Jaecklin, 1983).
These structures are known as vegetated cribwalls.
5. PURPOSE
Live cribwalls protect the toe and help retain steep streambanks. Live cuttings placed within the crib structure reinforce the cribfill. The tips of vegetation that protrude outside the crib face provide cover and shade for aquatic organisms and promote sediment accretion or build up at the toe.
6. PLANNING
Useful for Erosion Processes:
Toe erosion with upper bank failure Scour of middle and upper banks by currents Local scour Erosion of local lenses or layers of noncohesive sediment Erosion by overbank runoff General bed degradation Headcutting Piping Erosion by navigation waves Erosion by wind waves Erosion by ice and debris gouging General bank instability or susceptibility to mass slope failure
Spatial Application:
Instream Toe Midbank Top of Bank
Hydrologic / Geomorphic Setting
Resistive Redirective Continuous Discontinuous Outer Bend Inner Bend Incision Lateral Migration Aggradation Conditions Where Practice Applies:
Log cribwalls may be useful in areas where mass instability is the predominant mechanism of failure and where a near vertical structure is required to protect an eroding streambank. A live cribwall system is helpful at the base of slopes where a low toe-wall can be used to:
Protect a general reach of stream where floodplain encroachment has occurred
- Defend steep banks that cannot be regraded or cut back
- Protect local elements (such as existing trees) along the streambank that are endangered by bank erosion
- Reduce the steepness of a slope by filling behind the crib, thus making it easier to establish vegetation on the slope face and also to reduce the danger of surficial erosion above the structure
Complexity:
Moderate to High. Live cribwalls are relatively complex structures to design and to construct in comparison to other soil bioengineering techniques. They must be built to withstand both hydraulic loading (from stream scour) and lateral earth forces (from bank oversteepening).
Design Guidelines / Typical Drawings:
Crib structures must have adequate external and internal stability. External stability requires that a crib structure as a whole have sufficient bearing capacity and resist lateral forces that cause sliding and overturning. Internal stability requires that individual structural members be capable of resisting shear, moment and compression forces placed on them by both internal and external loads. Standard designs and specifications for conventional concrete and treated timber crib structures can be found in Gray and Leiser (1982) and Schwarzoff (1975). In live cribwalls, the structural members are usually untreated log or timber members. Limited design specifications for some types of log cribs can be found in Gray and Leiser (1982). Additional information about log cribwalls is provided by Washington State (2003). A schematic or conceptual design for a cribwall streambank protection can be seen in Figure 1. For the most part, live cribwalls have been designed and built in practice by a trial and error process without the benefit of rigorous analysis and promulgation of design specifications.
Figure 1. Schematic diagram/conceptual design of live cribwall (from USDA, 1996)
Live Cribwalls Typical Drawing
7. ENVIRONMENTAL CONSIDERATIONS / BENEFITS
A vertical structure at the toe minimizes or may avoid the need to flatten
the bank and encroach on the land behind the crest. A live cribwall has a
more natural appearance and is less visually intrusive than a structural treatment
alone, e.g., conventional cribwall, steel bulkhead, or gabion wall. Well established
vegetation in a live cribwall screens the structural elements from view and
gives the bank the appearance of a naturally vegetated steep bank. A well
vegetated (or revegetated) bank can improve aquatic and riparian habitat in
addition to providing important functional benefits (Coppin and Richards,
1990). The vegetation protruding beyond the cribwall face provides cover,
overhang, and shade for fish and other aquatic life near the water's edge.
8. HYDRAULIC LOADING
Uncertain effect on bank roughness, particularly as vegetation becomes established
in frontal openings of wall and/or flow velocity changes. Presence of well
established vegetation likely increases roughness at low velocities and
decreases at high (as vegetation bends over and flattens against front of
wall). Roughness can be enhanced by incorporating roughness elements such
as rootwads into the cribwall’s construction; however, this may also
cause some addition local scour due to exaggerated turbulence around them
(Washington State, 2003).
9. COMBINATION OPPORTUNITIES
Can be used in combination with mid and top of slope treatments (see Live
Staking, Live
Fascines, Brushlayering,
Erosion
Control Blankets, Turf
Reinforcement Mats, etc) and techniques specifically suited to
protect/defend the toe of streambanks (see Live
Siltation, Vegetated/Modified
Riprap, Large
Woody Debris Structures, etc.)
10. ADVANTAGES
Does not require slope flattening and regrading. Protects toe while increasing
bank roughness (with establishment of dense vegetation in wall and at low
velocities). Well vegetated cribwall promotes siltation and provides overhanging
shade and cover.
11. LIMITATIONS
Relatively complex and costly compared to other soil bioengineering treatments.
Design requires both geotechnical and structural analysis. A cribwall must
have a stable foundation and must be capable of resisting lateral loads
and overturning forces. The structure may be subject to undermining by scour;
which will require ancillary rock toe protection at the toe. The vertical
nature of cribwalls make them somewhat comparable to bridge abutments, and
studies have shown (Washington State, 2003)
that vertical bridge abutments incur twice the scour that sloped abutments
do. A cribwall requires time to design and construction is difficult and
impractical during high-flow events.
12. MATERIALS AND EQUIPMENT
The inert construction materials consist of logs or timbers ranging
from 10 cm to 15 cm (4 in to 6 in) in diameter (or greater depending on the
height of the structure and expected loading). Log cribwalls should be constructed
using logs that retain their strength for an acceptable period of time and
are resistant to rot. Cedar and spruce logs have a relatively high resistance
to rot, while soft wood, such as alder and pine, should be avoided. Galvanized
fasteners at the corners, e.g., spikes and lag bolts, must be of sufficient
size and diameter to withstand internal stresses resulting from the cribfill
and external forces acting on the structure. The cribfill can consist of native
soil, provided it is relatively cohesionless or coarse grained (sand, silty
sand, sandy silt, or non plastic silt). Live construction material
consists of the live cut branches placed inside the crib; they are normally
12.5 mm to 50 mm (0.5 in to 2 in) in diameter and long enough to extend beyond
the crib into the backfill and native soil behind the structure. Site preparation
and construction of cribwalls can be accomplished with hand labor, but a small
excavator is helpful for both. Logs can be cut and notched using a chain saw;
a power drill is needed to make the holes into which pins (or large spikes
or reinforcing bars) are driven to hold the log structure together.
13. CONSTRUCTION / INSTALLATION
Live cribwalls use dimensioned timbers or logs; preferably durable
material such as redwood or cedar. They are not intended to resist large,
lateral earth stresses, and should be constructed no higher than 1.8 m (6
ft). The following guidelines and procedures should be followed when constructing
a live cribwall system. Detailed installation/construction
guidelines can be found in Gray and Sotir (1996) and USDA (1996). Additional
information is provided by Washington State (2003).
Starting at the lowest point of the slope, excavate loose material 0.6 to 0.9 meters (2 to 3 ft) below the ground surface until a stable foundation is reached. The footing base should be inclined into the slope so that the structure will have a batter that provides additional stability to the structure.
Place the first course of logs or timbers at the front and back of the excavated foundation, approximately 1.2 m to 1.5 m (4 to 5 feet) apart and parallel to the slope contour. Place the next course of logs or timbers at right angles (perpendicular to the slope) on top of the previous course to overhang the front and back of the previous course slightly.
Each course of the live cribwall is placed in the same manner and fastened to the preceding course with spikes, lag bolts or reinforcing bars. This erection procedure results in an interlocking, box-like structure as shown in Figure 2.
When the cribwall structure reaches slightly above the existing ground surface (at the base), place live branch cuttings on the cribfill perpendicular to the slope as shown in Figure 3; then cover the cuttings with more cribfill and compact.
The live branch cuttings or branches should be placed at each course to the top of the cribwall structure with the growing tips extending from the back toward the front face. Follow each layer of branches with a layer of compacted soil to ensure soil contact with the branch cuttings.
14. COST
Live cribwalls are relatively more complex and expensive than other soil bioengineering techniques. Cost comparisons are provided in the table below.
UNIT COSTS FOR SOIL BIOENGINEERING MEASURES
Method Installed
|
Installed Unit Cost1 |
|||
Metric |
US |
|||
1994 Dollars |
2003 Dollars |
1994 Dollars |
2003 Dollars |
|
Live Staking |
$1.50 - $3.50 per stake |
$1.86 - $4.34 per stake |
$1.50 - $3.50 per stake |
$1.86 - $4.34 per stake |
Joint Planting |
$2.00 - $9.00 per stake |
$2.48 - $11.17 per stake |
$2.00 - 9.00 per stake |
$2.48 - $11.17 per stake |
Live Fascine |
$16.40 - $29.50 per lineal m |
$20.35 - $36.60 per lineal m |
$5.00 - 9.00 per lineal ft |
$6.20 - $11.17 per lineal ft |
Live cribwall |
$107.60 - $269 per m2 of front face |
$133.50 - $333.75 per m2 of front
face |
$10.00 - 25.00 per sq. ft of front face |
$12.41 - $31.02 per ft2 of front
face |
Brushlayer - Cut |
$26.24 - $42.64 per lineal m |
$32.56 - $52.90 per lineal m |
$8.00 - 13.00 per lineal ft |
$9.93 - $16.13 per lineal ft |
Brushlayer - Fill |
$39.36 - $82.00 per lineal m |
$48.83 - $101.74 per lineal m |
$12.00 - 25.00 per lineal ft |
$14.89 - $31.02 per lineal ft |
Vegetated Geogrid |
$39.36 - $98.40 per lineal m |
$48.83- $122.08 per lineal m |
$12.00 - 30.00 per lineal ft |
$14.89 - $37.22 per lineal ft |
Live Slope Grating |
$269 - $538 per m2 of front face | $333.75 - $667.49 per m2 of front face | $25.00 - 50.00 per sq. ft of front face | $31.02 - $62.03 per ft2 of front
face |
The unit costs of log cribwalls constructed in Washington State during the period 1995-2000 ranged from $825-$1,000 per m ($250-300 per ft) (Washington State, 2003). These costs included materials and construction only; not design and post construction costs. Approximate unit costs (in $1999) for live cribwalls constructed in Maryland ranged from $118 to $300 per square m ($11 to $28 per square ft) of front face (Maryland, 2000). These cost data are approximate and site specific; they should be used primarily for order-of-magnitude estimates and comparison purposes only.
15. MAINTENANCE / MONITORING
Inspect for evidence of excessive erosion from stream scour and undermining
at the toe of the cribwall. If erosion is excessive, the toe may need to
be armored with rock. The condition of the logs should be inspected periodically
for premature rotting. Eventual rotting is to be expected and should not
diminish the efficacy of the live cribwall system, because as vegetation
becomes well established, its root system provides the stability that would
otherwise be lost as log crib members decay over time.
16. COMMON REASONS / CIRCUMSTANCES FOR FAILURE
Selection of logs that rot too soon and do not maintain their structural integrity for an acceptable period of time.
Undermining by stream scour at the toe of the wall.
Inadequate transition at upstream and downstream ends of cribwall. If smooth transition is not created, turbulent eddies will result, and erosion of adjacent banks may occur.
17. CASE STUDIES AND EXAMPLES
A live cribwall was used in conjunction with other soil bioengineering treatments
to stabilize and protect a streambank on a small stream in Paulding County,
GA, known as Raccoon Creek. The stream has a mean daily flow of 15 m3/sec
(45 cfs). Raccoon Creek drains a watershed of about 78 sq. km (30 sq. mi.)
that was undergoing transition from rural residential or agricultural to
suburban land use. The live cribwall was used to protect a portion of the
streambank adjacent to a transmission tower that was located very close
to the bank edge (see Figure 4).
Figure 4. Live cribwall nearing completion. Note interlocking, box-like construction and live branches protruding between logs.
Racoon Creek, Georgia (from Gray and Sotir, 1996)
The bank at this location was originally protected by metal sheet piling
and rock riprap. This bank protection system was constantly being repaired
and rock replaced during a twelve-year period, prior to replacement with
soil bioengineering bank protection methods. The channel top width at
this location was approximately 15.25 m (50 ft), bottom width was about
9 m (30 ft), and bank height varied from 3 to 4.5 m (10 to 15 ft). Before
installing the live cribwall system, the riprap was removed and the sheet
piling cut off to allow good drainage behind the structure. Additional
systems installed upstream and downstream of the live cribwall at this
site included a live boom, brush mattressing, live fascines, and joint
planted (live staked) riprap. This bank protection system has performed
satisfactorily since its installation in the early 1980s. No further bank
erosion has occurred at the site, and other than periodic brush removal
in the immediate vicinity of the tower, no maintenance has been required
since installation.
Please visit the Photo Gallery for
more pictures.
18. RESEARCH OPPORTUNITIES
Determine the minimum period required for log longevity so that loss of
strength of structural members is compensated by mass stability provided
by monolithic earthen mass consisting of root permeated and reinforced cribfill
and natural soil. Determine in greater detail how establishment of vegetation
in cribwall face affects roughness over time and under varying flow regimes.
19. REFERENCES
Coppin, N. J., & Richards, I. (1990). Use
of Vegetation in Civil Engineering. Butterworths: Sevenoaks, Kent (England).
Gray, D. H. & Leiser, A. (1982). Biotechnical Slope Protection
and Erosion Control. Van Nostrand Reinhold, New York, N. Y.
Gray, D. H. & Sotir, R. (1996). Biotechnical and Soil
Bioengineering Slope Stabilization. John Wiley and Sons, New York, N.
Y.
Jaecklin, F.P. (1983). Retaining beautifully. Architect and Builder,
May 1983.
Maryland Department of the Environment, Water Management Administration
(Follweiler, J eds.) (2000). Maryland’s Waterway Construction Guidelines,
Section 3 Channel Stabilization and Rehabilitation Techniques, Baltimore,
MD. (pdf)
Schiechtl, H.M & Stern, R. (1998). Water Bioengineering Techniques
for Riverbank and Shore Stabilization. Blackwell Science, London, England
Schwarzoff, J.C. (1975). Retaining wall practice and selection for low-volume
forest roads. Transportation Research Board Special Report # 160,
pp. 128-140.
USDA Soil Conservation Service. (1996). Chapter 16: Streambank and Shoreline
Protection. Part 650, 210-EFH, Engineering Field Handbook, 88 pp.
(pdf)
Washington Dept of Fish & Wildlife (2003). Integrated Streambank Protection Guidelines, published in co-operation with Washington Dept. of Transportation and Washington Dept. of Ecology, June 2003. (Chapter 6 pdf) (Appendix L pdf) (Appendix H pdf) http://www.wa.gov/wdfw/hab/ahg/ispgdoc.htm (April 2003)